Earned value management,
explained with one project.

Earned value management compares three numbers: the work you planned to have done, the work actually done, and what it cost. From them you can tell whether a project is over budget, behind schedule, and where it's heading. One worked example.

In development: ZeroPlan

  1. 1. The three numbers

    Take a project with a budget of $10,000 (the budget at completion, BAC). At the end of week 4 you check where it stands.

    • Planned value (PV): the budgeted cost of the work planned by now. 50% planned × $10,000 = $5,000
    • Earned value (EV): the budgeted cost of the work actually done. 40% done × $10,000 = $4,000
    • Actual cost (AC): what has really been spent. $5,000
  2. 2. Variances: over or under

    Subtract to see how far off you are, in money. A negative number is bad news.

    • Cost variance, CV = EV − AC = $4,000 − $5,000 = −$1,000: over budget
    • Schedule variance, SV = EV − PV = $4,000 − $5,000 = −$1,000: behind schedule
  3. 3. Indices: how efficient

    Divide instead, to get ratios you can compare across projects. Below 1.0 is worse than planned; above 1.0 is better.

    • Cost performance index, CPI = EV ÷ AC = 0.8: each dollar spent earns 80 cents of work
    • Schedule performance index, SPI = EV ÷ PV = 0.8: work is getting done at 80% of the planned rate
  4. 4. Forecast the finish

    If the project keeps spending at the same efficiency, the estimate at completion is the budget divided by the CPI: $10,000 ÷ 0.8 = $12,500. That's $2,500 over, a warning you get at week 4 instead of at the end.

    • Estimate at completion, EAC = BAC ÷ CPI = $12,500
    • Variance at completion, VAC = BAC − EAC = −$2,500
  5. 5. Track it as you go

    Earned value works best measured often, from the same plan the schedule uses. ZeroPlan, from Black Zero Labs, keeps costs and earned value next to the schedule; it's in development and under testing, and not released yet.

Apps used

The apps behind it.

The apps are designed to open the same project, so nothing has to be exported between them. You'll install only the ones you use.

Questions

Good to know.

See the roadmap

1.0 means spending exactly as planned. Above 1.0 is under budget for the work done; below 1.0 is over. Small swings early in a project are normal; a steady drop is the thing to act on.

Early access

Know where it's
heading, early.

ZeroPlan is in development. Nothing can be downloaded or bought yet. Join the waitlist and we'll write when it opens.

We only use your email to tell you about early access. Privacy policy